Budget Estimate Reports for MAY 3, 2006 FDOT Bid Letting

|
| NO. | Ad No. | Proposal ID | FPN | Note | COUNTY | WORK-MIX | AMOUNT | DAYS | DIST. |

|
| #1 | Moved from 4/26/06 | T1180 Bid Items | 415443 1 52 01 | BB/LS/SS | COLLIER | RESURFACING | $3,235,316.00 | 145 | 1 |
| #2 | Moved from 5/3/06 | T1181 Bid Items | 418233 1 52 01 | FS | HENDRY | DRAINAGE IMPROVEMENTS | $2,119,278.00 | 120 | 1 |
| #3 | Moved from 4/26/06 | T2097 Bid Items | 209969 1 52 01 | LSB | PUTNAM | ADD LANES & RECONSTRUCT | $38,416,838.00 | 650 | 2 |
| #4 | Moved to 5/3/06 | T7120 Bid Items | 255599 1 52 01 | A+B/BB | HILLSBOROUGH | ADD LANES & RECONSTRUCT | $30,430,494.00 | 1000 | 7 |

|
| TOTAL BUDGET ESTIMATE = | $43,771,432.00 |
|

|
| ETC = | (More than one project no. within the contract) |
| * = | Jobs $150,000 or Less |
| ** = | Jobs $250,000 or Less |
| A+B |
A+B Bidding Project |
LS |
Lump Sum Bidding |
QC2000 |
QC2000 Pilot Project |
| LR |
Lane Rental Project |
P |
Partnering |
I-D |
Incentive/Disincentive |
| BAM |
Bid Averaging Method |
GC |
General Contractor |
LSB |
Liquidated Savings |
| M |
Metric |
MS |
Mandatory Start |
OCIP |
Owner Controlled Ins. Program |
| EA |
Early Award |
QP2 |
Lead Based Paint |
W |
Warranty |
| BB |
Bonus Bidding |
SS |
Special Start |
ASB |
Asbestos Abatement |
| UU |
Underground Utilities |
ASBS |
As-Built Survey |
PB |
Push Button |
| SO |
Specs Only |
% |
Electronic Plans |
LP |
Landscaping Prequalification |
| LSIC |
Lump Sum Innovative Contracting |
MPC |
Mandatory Prebid Conference |
# |
$300 Job (Plan/Spec or Proposal) |
|
|
 |