Budget Estimate Reports for June 28, 2006 FDOT Bid Letting


NO.Ad No.Proposal IDFPNNoteCOUNTYWORK-MIXAMOUNTDAYSDIST.

#1T1147
Bid Items
197705 1 52 01A+B/I-DPOLKADD LANES & REHABILITATE PVMNT$29,827,379.00 6751
#2Moved from 6/21/06T3092
Bid Items
222590 2 52 01A+B/LR/MPCLEONADD LANES & RECONSTRUCT$39,449,416.00 10103
#3Moved from 6/21/06T5153
Bid Items
242702 2 52 01A+BVOLUSIAINTERCHANGE (MAJOR)$16,844,000.00 4505
#4Moved from 6/21/06T5155
Bid Items
415525 1 52 01FSORANGERESURFACING$2,901,247.00 2565
#5T7070
Bid Items
257070 1 52 01A+BPINELLASADD LANES & RECONSTRUCT$70,816,688.00 9557

TOTAL BUDGET ESTIMATE =$159,838,730.00

ETC = (More than one project no. within the contract)
* = Jobs $150,000 or Less
** = Jobs $250,000 or Less

A+B A+B Bidding Project LS Lump Sum Bidding QC2000 QC2000 Pilot Project
LR Lane Rental Project P Partnering I-D Incentive/Disincentive
BAM Bid Averaging Method GC General Contractor LSB Liquidated Savings
M Metric MS Mandatory Start OCIP Owner Controlled Ins. Program
EA Early Award QP2 Lead Based Paint W Warranty
BB Bonus Bidding SS Special Start ASB Asbestos Abatement
UU Underground Utilities ASBS As-Built Survey PB Push Button
SO Specs Only % Electronic Plans LP Landscaping Prequalification
LSIC Lump Sum Innovative Contracting MPC Mandatory Prebid Conference # $300 Job (Plan/Spec or Proposal)