Budget Estimate Reports for October 25, 2006 FDOT Bid Letting

|
| NO. | Ad No. | Proposal ID | FPN | Note | COUNTY | WORK-MIX | AMOUNT | DAYS | DIST. |

|
| #1 | | T1202 Bid Items | 417249 1 52 01 | LS/MPC | HARDEE | RESURFACING | $1,721,743.00 | 90 | 1 |
| #2 | | T1206 Bid Items | 196960 3 52 01 | BB/LS | POLK | RESURFACING | $1,433,789.00 | 80 | 1 |
| #3 | | T4134 Bid Items | 413802 1 52 01 | LS | MARTIN | RESURFACING | $2,154,091.00 | 141 | 4 |
| #4 | | T4139 Bid Items | 413801 1 52 01 | LS | PALM BEACH | RESURFACING | $11,129,408.00 | 420 | 4 |

|
| TOTAL BUDGET ESTIMATE = | $16,439,031.00 |
|

|
| ETC = | (More than one project no. within the contract) |
| * = | Jobs $150,000 or Less |
| ** = | Jobs $250,000 or Less |
| A+B |
A+B Bidding Project |
LS |
Lump Sum Bidding |
QC2000 |
QC2000 Pilot Project |
| LR |
Lane Rental Project |
P |
Partnering |
I-D |
Incentive/Disincentive |
| BAM |
Bid Averaging Method |
GC |
General Contractor |
LSB |
Liquidated Savings |
| M |
Metric |
MS |
Mandatory Start |
OCIP |
Owner Controlled Ins. Program |
| EA |
Early Award |
QP2 |
Lead Based Paint |
W |
Warranty |
| BB |
Bonus Bidding |
SS |
Special Start |
ASB |
Asbestos Abatement |
| UU |
Underground Utilities |
ASBS |
As-Built Survey |
PB |
Push Button |
| SO |
Specs Only |
% |
Electronic Plans |
LP |
Landscaping Prequalification |
| LSIC |
Lump Sum Innovative Contracting |
MPC |
Mandatory Prebid Conference |
# |
$300 Job (Plan/Spec or Proposal) |
|
|
 |