Home Contact Us
About Us Membership Committees Bids Specs Const. Issues Gov. Affairs Training Courses Resources
Bids
Budget Estimate Reports for March 5, 2008 FDOT Bid Letting


NO.Ad No.Proposal IDFPNNoteCOUNTYWORK-MIXAMOUNTDAYSDIST.

#1T1232
Bid Items
197043 2 52 01LSPOLKRESURFACING$1,753,195.00 751
#2T1260
Bid Items
416116 1 52 01I-D/LS/SSSARASOTAINTERSECTION (MODIFY)$3,183,804.00 1751
#3T3164
Bid Items
415257 1 52 01GADSDENRESURFACING$25,000,000.00 3703
#4T4180
Bid Items
413843 1 52 01FS/I-D/LSPALM BEACHRESURFACING$3,251,785.00 1934
#5T4181
Bid Items
228583 5 52 01I-DINDIAN RIVERADD LANES & RECONSTRUCT$28,542,800.00 7564
#6T4183
Bid Items
413844 1 52 01LSMARTINRESURFACING$7,240,399.00 1924
#7T5229
Bid Items
437576 2 52 01A+BBREVARDWIDEN/RESURFACE EXIST LANES$31,735,964.00 6605
#8T5230
Bid Items
415464 1 52 01VOLUSIATRAFFIC OPS IMPROVEMENT$4,091,091.00 1805
#9T5231
Bid Items
417179 1 52 01LSMARIONRESURFACING$3,611,842.00 1005
#10T5235
Bid Items
412206 1 52 01LSVOLUSIABRIDGE-REPAIR/REHABILITATION$1,222,260.00 2405
#11T5236
Bid Items
421645 1 52 01LSSUMTERPERIODIC MAINTENANCE$3,007,242.00 2105
#12T7185
Bid Items
411334 1 52 02FS/LSPASCORESURFACING$4,171,700.00 1807

TOTAL BUDGET ESTIMATE =$116,812,082.00

ETC = (More than one project no. within the contract)
* = Jobs $150,000 or Less
** = Jobs $250,000 or Less

A+B A+B Bidding Project LS Lump Sum Bidding QC2000 QC2000 Pilot Project
LR Lane Rental Project P Partnering I-D Incentive/Disincentive
BAM Bid Averaging Method GC General Contractor LSB Liquidated Savings
M Metric MS Mandatory Start OCIP Owner Controlled Ins. Program
EA Early Award QP2 Lead Based Paint W Warranty
BB Bonus Bidding SS Special Start ASB Asbestos Abatement
UU Underground Utilities ASBS As-Built Survey PB Push Button
SO Specs Only % Electronic Plans LP Landscaping Prequalification
LSIC Lump Sum Innovative Contracting MPC Mandatory Prebid Conference # $300 Job (Plan/Spec or Proposal)