Budget Estimate Reports for May 21, 2008 FDOT Bid Letting

|
| NO. | Ad No. | Proposal ID | FPN | Note | COUNTY | WORK-MIX | AMOUNT | DAYS | DIST. |

|
| #1 | Ad #2 | T1274 Bid Items | 422664 1 52 01 | */LS | HIGHLANDS | SIGNING/PAVEMENT MARKINGS | $128,500.00 | 40 | 1 |
| #2 | Ad #2 | T1275 Bid Items | 422665 1 52 01 | **/LS | POLK | LIGHTING | $178,437.00 | 75 | 1 |
| #3 | Ad #2 | T1277 Bid Items | 412622 1 52 01 | **/FL/LS | SARASOTA | SIDEWALK | $242,032.00 | 50 | 1 |
| #4 | Ad #2 | T1278 Bid Items | 422667 1 52 01 | **/LS | POLK | SIGNING/PAVEMENT MARKINGS | $229,649.00 | 50 | 1 |
| #5 | Ad #2 | T2180 Bid Items | 210408 3 52 01 | | ST. JOHNS | INTERSECTION (MODIFY) | $3,096,849.00 | 180 | 2 |
| #6 | Ad #2 | T2195 Bid Items | 208628 2 52 01 | | DUVAL | INTERSECTION (MODIFY) | $5,012,348.00 | 260 | 2 |
| #7 | Ad #2 | T3262 Bid Items | 422504 1 52 01 | FS | WASHINGTON | TRAFFIC SIGNALS | $438,485.00 | 80 | 3 |
| #8 | | T4187 Bid Items | 406870 2 52 01 | I/D | PALM BEACH | ADD LANES & RECONSTRUCT | $68,922,300.00 | 1380 | 4 |
| #9 | | T4196 Bid Items | 413842 1 52 01 | ETC/LS | PALM BEACH | RESURFACING | $21,187,542.00 | 470 | 4 |
| #10 | Ad #2 | T4197 Bid Items | 413795 1 52 01 | I/D | BROWARD | RESURFACING | $6,148,958.00 | 232 | 4 |
| #11 | Ad #2 | T4198 Bid Items | 413886 1 52 01 | | BROWARD | RESURFACING | $2,801,850.00 | 158 | 4 |
| #12 | Moved to 6/18/08 | T4199 Bid Items | 41384515201 | | MARTIN | RESURFACING | 4196263 | 210 | 4 |
| #13 | Ad #2 | T5239 Bid Items | 239442 1 52 01 | | ORANGE | RIGID PAVEMENT REHABILITATION | $3,193,323.00 | 280 | 5 |
| #14 | Ad #2 | T5243 Bid Items | 419557 1 52 01 | | MARION | RESURFACING | $2,747,070.00 | 100 | 5 |
| #15 | Ad #2 | T6115 Bid Items | 412475 1 52 01 | I-D/SS | MIAMI-DADE | RESURFACING | $4,517,588.00 | 310 | 6 |
| #16 | Ad #2 | T6157 Bid Items | 421240 1 52 01 | FS | MONROE | EMERGENCY OPERATIONS | $8,741,992.00 | 360 | 6 |
| #17 | Moved to 6/4/08 | T7192 Bid Items | 25729825201 | ETC/SS | HERNANDO | ADD LANES & RECONSTRUCT | 29125000 | 700 | 7 |
| #18 | Ad #2 | T7195 Bid Items | 419198 1 52 01 | | HILLSBOROUGH | SKID HAZARD OVERLAY | $1,167,921.00 | 75 | 7 |

|
| TOTAL BUDGET ESTIMATE = | $128,754,844.00 |
|

|
| ETC = | (More than one project no. within the contract) |
| * = | Jobs $150,000 or Less |
| ** = | Jobs $250,000 or Less |
| A+B |
A+B Bidding Project |
LS |
Lump Sum Bidding |
QC2000 |
QC2000 Pilot Project |
| LR |
Lane Rental Project |
P |
Partnering |
I-D |
Incentive/Disincentive |
| BAM |
Bid Averaging Method |
GC |
General Contractor |
LSB |
Liquidated Savings |
| M |
Metric |
MS |
Mandatory Start |
OCIP |
Owner Controlled Ins. Program |
| EA |
Early Award |
QP2 |
Lead Based Paint |
W |
Warranty |
| BB |
Bonus Bidding |
SS |
Special Start |
ASB |
Asbestos Abatement |
| UU |
Underground Utilities |
ASBS |
As-Built Survey |
PB |
Push Button |
| SO |
Specs Only |
% |
Electronic Plans |
LP |
Landscaping Prequalification |
| LSIC |
Lump Sum Innovative Contracting |
MPC |
Mandatory Prebid Conference |
# |
$300 Job (Plan/Spec or Proposal) |
|
|
 |