This challenging renovation was completed by the Allstate Team while maintaining a safe
environment for 20,000 plus students passing through the complex each day. Phase One
Construction included replacement of approximately 60,000 s.f. of roofing. Phase Two
provided for utility upgrades, asbestos abatement and the construction of a new food
services court. Phase Three completed the project with accessibility upgrades, bathroom
renovations, a complete renovation of the third floor of the activities building for
student government facilities and renovations for new conference and meeting room space.